Quick Answer:
Use a twelve-field RFQ to define the circuit, exact block configuration, conductor schedule, mounting, environment, accessories, evidence and commercial basis. Require every supplier to answer each field with Confirmed, Exception, Alternative proposed or Not applicable. Then compare offers by line, not by headline price.
The buyer controls the common requirement; suppliers must expose deviations and cite model-specific documents. That discipline turns a catalogue response into a checkable quotation and shows which differences need engineering or commercial approval before order.
Two quotes can name the same product category and still describe different purchases. One assumes a single input and output; another covers several branches. One includes a cover and markers; another lists them as extras. One cites a catalogue page; another identifies the exact drawing and model revision.
A power distribution block RFQ template fixes those variables before suppliers quote: one requirement set, one response format and a visible record of exceptions.
What makes distribution-block quotes hard to compare?
The term covers compact DIN-rail blocks, panel-mounted power feeds and one-input, multi-output configurations. Function, conductor range and accessories can change within one product family.
HAIYAN’s FJ6/JTS3-150 series page shows why the exact order code matters. It lists a one-input, one-output variant and versions with 2, 3, 4, 6, 8, 9 or 12 outputs. The input range is 35–150 mm²; output ranges vary by variant. The 150 in the name is not proof of a 150 A rating.
If you are still shortlisting, start with the distribution blocks category, then define the circuit role. Freeze the candidate model before requesting commercial offers.
Which 12 fields should your RFQ control?
Use the same field order for every supplier. Do not let rows be deleted or merged.
| RFQ field | What the buyer must state | Required supplier answer |
|---|---|---|
| 1. Identity and boundary | Project, RFQ revision, deadline, destination, currency, validity, alternatives allowed? | Quote reference, revision, assumptions, contact |
| 2. Installed function | Feeder or branch distribution; N, PE or equipotential role; shared potential? | Confirm function or state exception |
| 3. Electrical duty | Voltage, frequency, phases, load/current profile, ambient, enclosure; SCCR or fault context only if project-specified | Confirm basis and model limits |
| 4. Line-side conductors | Material, exact mm² or AWG, construction, preparation, termination, quantity | State acceptance by conductor type and preparation |
| 5. Load-side branches | Output count, conductor details, grouping, spare ways, identification | Map each branch to the offered configuration |
| 6. Topology and model | Input/output count, poles, potentials, connection method, full order code, alternative rule | Give exact configuration or documented alternative |
| 7. Mounting and envelope | DIN rail or panel mounting, interface, orientation, clearance, CAD constraints | Cite drawing and confirm envelope |
| 8. Materials and environment | Conductor, insulator, plating; protection, temperature, contamination, label durability | Model-specific declaration or exception |
| 9. Accessories | Covers, markers, labels, end stops, hardware, packaging; included or priced separately? | Itemize included and excluded items |
| 10. Evidence | Drawing, datasheet, declaration, certificate or test evidence; revision; sample or FAI need | Document ID, revision, page or test condition |
| 11. Commercial basis | Quantity by model, samples, MOQ, pack multiple, price basis, tooling/NRE, packaging, delivery definition, Incoterm and place | Price and supply the same basis without hidden assumptions |
| 12. Deviations and change | Substitution rule, change notification, traceability, approval contact | List every deviation, substitution and open item |
Those fields go beyond a datasheet. A technically acceptable block can still produce a poor purchase when accessories, document revision, quantity basis or delivery definition differ between offers.

How should you request proof for the exact offer?
Ask for evidence tied to the offered item, not the product family. A document needs an identifier, revision and relevant page or test condition. “Certificate available” is not enough if the buyer cannot tell which model or configuration it covers.
The distribution block selection guide explains the selection context before an RFQ is issued. The supplier response should narrow that context to the exact order code.
Three checks catch weak evidence:
- Match the document to the offered model, not just the series name.
- Keep N and PE as separate functions. Similar shape or shared hardware does not make them interchangeable.
- Treat SCCR, environmental protection and approvals as project and model requirements. Ask for the applicable evidence rather than inferring it from the category.
State the conductor preparation method too. mm² describes cross-sectional area, not diameter. A fine-stranded conductor with a ferrule can behave differently at the terminal from a bare stranded conductor of the same nominal size. Confirm the accepted range and condition for the exact model.
How do you compare quotes without hiding deviations?
Compare the supplier answers first, then the prices. A missing answer is not a pass. Every row should end as Confirmed, Exception, Alternative proposed or Not applicable. The labels make silence visible and give engineering, quality and procurement one record.
Keep the same row order for every supplier in the distribution block quote comparison.
| Comparison check | Accept only when | Escalate when |
|---|---|---|
| Model and topology | Order code, input/output count and function match | Different model without a written alternative |
| Conductor fit | Material, construction, preparation and range confirmed for the exact model | Reply relies on nominal size alone |
| Mounting and accessories | Drawing, envelope and included items identifiable | Critical items called “standard” but unlisted |
| Electrical evidence | Cited document matches model and stated conditions | Ratings or SCCR appear only in marketing text |
| Commercial basis | Quantity, MOQ, pack, delivery definition and Incoterm place explicit | Lead time has no start point or delivery term |
| Deviations | Every exception has an owner and approval status | Silence presented as compliance |
The lowest price is comparable only after these rows agree. An exception is not automatically a rejection; it needs review and a documented decision. A substitution is not the requested product until the responsible design or approval authority accepts it.


Product Features • Power distribution terminal block with one input and multiple outputs for multi-circuit power and circuit distribution. • Direct conductor connection (screw clamping). • Protective cover fits securely and remains firmly…
View Product DetailsHow should you send the RFQ and record responses?
The table is the specification; the cover note is the control. Put both in one technical RFQ so a supplier cannot answer a narrow product question while ignoring the order conditions.
RFQ: [project] Revision: [ ]
Quote basis: [exact model/order code] Alternatives: [allowed / not allowed]
Circuit: [function; voltage; frequency; phases; load profile]
Line side: [material; mm² or AWG; construction; preparation; quantity]
Load side: [output count; conductor details; grouping; identification]
Mounting: [DIN rail or panel; orientation; envelope constraints]
Evidence: [document; revision; model reference; sample or FAI requirement]
Commercial: [quantity; destination; Incoterm place; currency; validity]
Response: one row per field, each marked Confirmed / Exception / Alternative proposed / Not applicable
Ask suppliers to return the completed table plus a deviation log. The log should give the affected field, proposed alternative, reason, effect on price or schedule, and the approval owner. Treat a blank cell as an open question, not agreement.
Before awarding, check that the quoted order code, drawing revision and included accessories match the response. If a supplier proposes a different block, restart the comparison against the same twelve fields; the alternative does not inherit the original offer’s assumptions.
For a project RFQ, send HAIYAN the circuit layout, conductor schedule, quantities, destination and required documents through its selection and BOM support process. Those inputs let the discussion start with the exact configuration and evidence rather than a generic catalogue price.